Tuesday, 13 November 2012

The mezzanine begins.

Sorted a lot of the interior stuff and have begun to connect up the steel structure inside the shed. Managed to connect the long beam at the weekend and can now measure the remaining spans before ordering the last lot of steel.  I'm aiming to have it all purchased so it can be installed over the holidays.




Thursday, 27 September 2012

Inside work begins

Started on my new workbench and also began to section off the storage area. Poured some concrete and added the vertical strut for the mezzanine construction. Bits and pieces to do before we see anything significant happening, but that's always the way. It's easier now I can find my tools and have a bench with a vice. Things just happen a bit quicker.



Wednesday, 19 September 2012

Passed the inspection.

Rang the surveyor on Monday and organised the visit by the inspector. He checked out the building on Tuesday and when I spoke to them on Wednesday everything was fine and will be sent off to Brimbank council etc in the near future. Now I can begin building the sections they don't know about, ie. internal walls and the mezzanine floor. Fantastic, can even begin some of the backyard work.

Saturday, 15 September 2012

Finished at last

309 days after having the concrete slab poured, the shed is finally complete. Not almost complete,but fully. Not another bolt, screw, fiddly little crap stuff etc. the whole thing is done. I fitted the two door handles today, touched up the paint work that was scratched and made a few minute adjustments. I will ring the surveyor on Monday and organise the final inspection. Once this has been approved I can move on to the next stage which will be to organise the inside with shelving for my tools, add the vices to my new woodworking bench and generally find a home for everything. I also have to formalise my plans for the mezzanine floor and after that the wall between the storage area and the workshop can be built.



Sunday, 9 September 2012

Doors are now complete

Spent the day finishing off the double doors. Managed to attach them with some assistance and adjusted them carefully so they aligned properly. The attention to detail as I constructed the doors paid off handsomely once they were ready to be attached to the frames. The locks are the final job and I hope to complete those during the week. It's almost finished and ready for final inspection.


Sunday, 12 August 2012

First door is on!

After a lot of fiddling with plans and adjusting the doors as I progressed I've finally got the first one finished and hanging nicely. Looks good and once the painting is completed I will instal the locking mechanism. It's time to start the double doors.



Saturday, 21 July 2012

Hanging the doors.

Picked up the door frames on Friday evening and worked on the preparation of the door trims today. Finally worked my way through the necessary cutting and measuring of the those and once finished they really add a completed look. Once they were installed I did a quick fit of the doors. The single door is a bit tight and will need some attention tomorrow before I can fit that, however once Cal returned from training I used him and we fitted the double doors.  They'll need some final adjustment as well tomorrow but once that's done I can add the spandek cladding and install the locks etc. It's nearly all done!